NuFlow lined over 1 mile of fire suppression systems within the Washington Metropolitan Area Transit Authority. The need to replace those pipes would have required significant downtime and impact on the operations of the subway.
Project: At each of eight Metro stations, coat 300 feet of variously sized fire suppression pipes.
Site: Eight stations within the Washington Metropolitan Area Transit Authority.
System: Fire suppression main for each station consisting of 300 feet of ductile, black iron, and galvanized pipes ranging from 1 1/2” to 6” in diameter.
Situation: The fire suppression systems were showing leaks and corrosion buildup that could jeopardize the performance of the fire suppression system.
Solution: NuFlow saved the customer from the high cost and complex logistics of repairing and replacing the entire system.