No Dig, Big Impact: How CIPP Lining Saved Time and Costs for a Hospital Expansion

When a local children’s hospital needed to renovate a newly acquired facility for a skilled nursing and subacute center, outdated cast iron pipes posed a major challenge. A full excavation and pipe replacement would have been costly, invasive, and time-consuming, delaying the facility’s opening. Instead, Bill Howe Plumbing, a NuFlow Certified Contractor, introduced CIPP lining, rehabilitating 1,670 linear feet of underground piping with minimal disruption. This trenchless solution not only saved costs but also accelerated project completion, ensuring the hospital could begin serving patients sooner.

The Problem: Aging Infrastructure Delays Expansion

The hospital had acquired a vacant mid-century facility adjacent to its main campus, planning to convert it into a skilled nursing and subacute center for children and adolescents with complex medical needs. To meet the specialized infrastructure requirements, significant upgrades were necessary including the replacement of deteriorating cast iron waste pipes.

The original plan called for saw-cutting, excavating, and replacing all underground waste piping connected to 152 fixtures. This method would have been highly disruptive and expensive, delaying the project and increasing costs.

Seeking a faster, more efficient solution, the hospital’s General Contractor worked with Bill Howe Plumbing, who recommended NuFlow’s NuDrain Cured-In-Place Pipe (CIPP) lining. After an on-site demonstration, all parties agreed that trenchless pipe rehabilitation was the best approach.

The Challenge: Strict Timelines & Limited Access

Several challenges required meticulous planning and coordination:

  • Aggressive project timeline: The facility needed to open as soon as possible, requiring simultaneous work on opposite sides of the property.
  • Comprehensive pipe rehabilitation: The client requested that every pipe, fitting, and connection be lined, leaving no section untouched.
  • Restricted workspace: With multiple trade contractors working on-site, accessibility to piping and workspaces was limited.
  • Minimal staging area: The wet-out area was small, making material storage and equipment placement more difficult.

With these challenges in mind, the project required precise execution and coordination to meet the hospital’s strict timeline.

The Solution: Trenchless Pipe-Lining with NuFlow’s NuDrain CIPP

To ensure efficiency, Bill Howe Plumbing worked closely with the General Contractor to implement strategic logistics and minimize disruptions.

Key Steps in the Process:

  • CIPP Lining for 1,670 Linear Feet: All underground cast iron waste pipes were rehabilitated without excavation.
  • Minimal Excavation: Only eight manual access points were created to install cleanouts on 4″ and 6″ main sewer lines.
  • Connection Liners & Brush Coating: The team used the Picote connection collar system to install 37 connection liners and apply brush coating to water closet trap arms.
  • Efficient Project Execution: Despite the challenges, the entire project was completed in just 77 days, staying ahead of schedule.

By utilizing trenchless technology, the hospital was able to fast-track construction, allowing other contractors to begin work months earlier than originally planned.

The Outcome: Faster Completion & Significant Cost Savings

By choosing NuFlow’s trenchless pipe repair, the hospital and General Contractor achieved major cost savings while accelerating the project timeline.

  • Avoided full pipe replacement, reducing labor and material costs.
  • Eliminated extensive excavation, minimizing disruption.
  • Completed work in 77 days, ensuring the facility could open sooner.

The hospital and General Contractor praised the efficiency and effectiveness of the NuFlow system, emphasizing how trenchless technology helped bring this critical care facility online faster—benefiting children in need of specialized medical support.

Conclusion: A Smarter Approach to Pipe Rehabilitation

This case study highlights how CIPP lining with NuFlow’s NuDrain system delivers fast, cost-effective pipe rehabilitation for healthcare and commercial projects. By eliminating excavation, reducing costs, and keeping projects on schedule, trenchless technology is redefining infrastructure rehabilitation in the healthcare industry.

Contact NuFlow today to learn how our trenchless solutions can keep your project on track while minimizing costs and disruptions.

Location

Local children’s hospital, mid-century facility adjacent to the hospital’s main campus

Situation

The hospital acquired a vacant building to convert into a skilled nursing and subacute center for children and adolescents with complex medical needs. The facility’s aging cast iron plumbing system was severely deteriorated, requiring full rehabilitation. The original plan involved excavation and full pipe replacement, which would have been costly, highly disruptive, and time-consuming. A faster, non-invasive solution was needed to ensure the facility could open on schedule.

Solution

NuFlow’s NuDrain Cured-In-Place Pipe (CIPP) lining was used to rehabilitate 1,670 linear feet of cast iron piping without excavation. The project was completed in 77 days, significantly accelerating the facility’s opening. Work was strategically planned to minimize disruptions and allow other trades to begin work months earlier than expected.

Products/Skills

NuDrain CIPP (Cured-In-Place Pipe) lining, Picote connection collar system for 37 connection liners, Brush coating application for water closet trap arms, Strategic project management and logistics to work around other trade contractors, Manual excavation for installing cleanouts on the 4

Join icon-nuflow Today!

Begin the path to new expertise, product offerings, and revenue streams. NuFlow technicians are highly-qualified educators and can offer the industry expertise, guidance, and resources to help you start installing state-of-the-art NuFlow products in no time.

icon-nuflow

Let’s get started!

"*" indicates required fields

This field is for validation purposes and should be left unchanged.

Scroll to Top